Permit Streamlining Deadlines Explained

‍ ‍

How California Is Putting a Clock on the Housing Approval Process

‍ ‍

For anyone who has worked on a development project, one of the most frustrating questions is often:

‍ ‍

“How long is this going to take?”

‍ ‍

Historically, the answer could be difficult to predict.

‍ ‍

An application might sit with an agency for weeks before an applicant learned something was missing. Corrections could trigger additional information requests. Hearings could be continued repeatedly. Months could pass before a project received a decision.

‍ ‍

California has increasingly responded by putting actual deadlines on parts of the permitting process.

‍ ‍

Through the Permit Streamlining Act, the Housing Crisis Act, SB 35/SB 423, and other housing legislation, state law now establishes timelines and procedures intended to prevent qualifying housing applications from remaining in review indefinitely.

‍ ‍

For property owners, builders, developers, and investors, understanding these deadlines can be extremely valuable.

‍ ‍

‍ ‍

What Is the Permit Streamlining Act?

‍ ‍

California’s Permit Streamlining Act establishes procedures state and local agencies must follow when processing many development applications.

‍ ‍

One of its most important requirements involves determining whether an application is complete.

‍ ‍

For covered applications, a local agency generally has 30 calendar days after receiving the application to notify the applicant in writing whether it is complete.

‍ ‍

If the application is incomplete, the agency must identify the missing information.

‍ ‍

When the applicant resubmits, another 30-day review period generally begins.

‍ ‍

If the agency fails to make the completeness determination within the statutory period, the application may be deemed complete under state law.

‍ ‍

‍ ‍

Why Does “Complete” Matter So Much?

‍ ‍

Anyone who works in permitting knows that submitting an application and having a complete application are two very different things.

‍ ‍

An application may be submitted but still be missing:

‍ ‍

·       Plans.

‍ ‍

·       Studies.

‍ ‍

·       Technical reports.

‍ ‍

·       Required forms.

‍ ‍

·       Fees.

‍ ‍

·       Supporting documentation.

‍ ‍

Many important statutory timelines don’t begin until an application is considered complete.

‍ ‍

That makes the completeness determination an important milestone in the entitlement process.

‍ ‍

‍ ‍

Agencies Can’t Keep Moving the Goalposts

‍ ‍

Another important protection involves correction requests.

‍ ‍

If an agency determines an application is incomplete, it must identify the missing information based on its application requirements.

‍ ‍

For qualifying housing applications, when the applicant resubmits, the agency generally cannot simply introduce entirely new completeness requirements that weren’t identified during the initial review.

‍ ‍

This helps prevent an application from becoming trapped in an endless cycle:

‍ ‍

Submit.

‍ ‍

Receive corrections.

‍ ‍

Resubmit.

‍ ‍

Receive completely different corrections.

‍ ‍

Resubmit again.

‍ ‍

The goal is to create a defined path toward completeness.

‍ ‍

‍ ‍

SB 330 and the Preliminary Application

‍ ‍

The Housing Crisis Act of 2019, commonly associated with SB 330, created another important tool for housing developers: the preliminary application.

‍ ‍

A developer can submit specified preliminary information before completing the entire development application.

‍ ‍

Once the statutory requirements and processing fee are submitted, the preliminary application can generally freeze or “vest” many of the ordinances, policies, standards, and fees that apply to the project at that time.

‍ ‍

The developer then generally has 180 days to submit the full development application.

‍ ‍

This can be extremely important when zoning standards or development fees are changing.

‍ ‍

‍ ‍

Limits on Endless Public Hearings

‍ ‍

California has also placed limits on how many hearings qualifying housing projects can be forced to undergo.

‍ ‍

For certain housing developments that comply with applicable objective General Plan and zoning standards, jurisdictions are generally limited to five hearings after the application is complete.

‍ ‍

Continued hearings count toward that total.

‍ ‍

The jurisdiction must take action to approve or disapprove the application during one of those hearings.

‍ ‍

This is intended to prevent projects from being delayed through repeated hearings without a final decision.

‍ ‍

‍ ‍

SB 35 and SB 423: Streamlined Ministerial Approval

‍ ‍

Some housing projects may qualify for an even more streamlined process.

‍ ‍

SB 35 created California’s Streamlined Ministerial Approval Process, and SB 423 subsequently expanded and modified it.

‍ ‍

Qualifying multifamily projects in jurisdictions that haven’t made sufficient progress toward their housing obligations—or in certain cases lack a compliant Housing Element—may be eligible for ministerial rather than traditional discretionary review.

‍ ‍

That distinction matters.

‍ ‍

Discretionary review allows more subjective governmental decision-making and can trigger CEQA.

‍ ‍

Ministerial review focuses primarily on whether the project complies with applicable objective standards.

‍ ‍

For qualifying developments, this can dramatically change both the timeline and predictability of the entitlement process.

‍ ‍

‍ ‍

Environmental Review Has Its Own Timelines

‍ ‍

Permit streamlining does not mean CEQA disappears.

‍ ‍

Projects requiring environmental review still must comply with CEQA.

‍ ‍

However, once environmental review is completed, state law establishes additional decision deadlines for certain housing projects.

‍ ‍

For example, under applicable Permit Streamlining Act provisions, a jurisdiction generally has 90 days after certification of an Environmental Impact Report to approve or disapprove a residential project, with the period reduced to 60 days for certain projects containing at least 49 percent affordable housing.

‍ ‍

‍ ‍

Why Investors Should Care

‍ ‍

Permit timelines aren’t merely administrative details.

‍ ‍

Time is part of the cost of development.

‍ ‍

Every additional month can mean:

‍ ‍

·       Loan interest.

‍ ‍

·       Property taxes.

‍ ‍

·       Insurance.

‍ ‍

·       Consultant costs.

‍ ‍

·       Construction inflation.

‍ ‍

·       Opportunity cost.

‍ ‍

·       Investor uncertainty.

‍ ‍

A project that takes three years to entitle may have completely different economics than one that takes eighteen months.

‍ ‍

Understanding which statutory deadlines apply allows investors to estimate development risk more accurately.

‍ ‍

‍ ‍

The Deadline Doesn’t Mean the Project Is Automatically Approved

‍ ‍

This is an important distinction.

‍ ‍

California’s streamlining laws don’t mean an applicant can simply submit plans, wait 30 or 60 days, and automatically start construction.

‍ ‍

Different deadlines apply to different stages and different types of projects.

‍ ‍

Projects may still require:

‍ ‍

·       Planning approvals.

‍ ‍

·       CEQA review.

‍ ‍

·       Building permits.

‍ ‍

·       Fire review.

‍ ‍

·       Public Works approval.

‍ ‍

·       Environmental Health approval.

‍ ‍

·       Utility approvals.

‍ ‍

·       Outside agency permits.

‍ ‍

The real advantage is that agencies increasingly have defined procedures and timelines they must follow.

‍ ‍

‍ ‍

What Happens When an Agency Misses a Deadline?

‍ ‍

The consequence depends on the particular law and deadline involved.

‍ ‍

In some circumstances, an application may be deemed complete.

‍ ‍

In others, applicants may have enforcement remedies available under California housing law.

‍ ‍

The California Department of Housing and Community Development’s Housing Accountability Unit also investigates potential violations of state housing laws and works with jurisdictions to bring them into compliance.

‍ ‍

Knowing that a deadline exists gives an applicant something extremely valuable:

‍ ‍

A legal framework for pushing a stalled project forward.

‍ ‍

‍ ‍

Rural California

‍ ‍

Permit streamlining matters in rural counties too, but rural projects often involve more agencies.

‍ ‍

A project might require coordination with:

‍ ‍

·       Environmental Health.

‍ ‍

·       Fire districts.

‍ ‍

·       CalFire.

‍ ‍

·       California Department of Fish and Wildlife.

‍ ‍

·       Regional Water Quality Control Boards.

‍ ‍

·       Caltrans.

‍ ‍

·       Utility providers.

‍ ‍

·       Other state or federal agencies.

‍ ‍

A deadline imposed on the local planning department doesn’t necessarily control the review timeline of every outside agency.

‍ ‍

That is why identifying all required approvals early is particularly important for rural development.

‍ ‍

‍ ‍

Common Misconceptions

‍ ‍

“Every permit has to be approved within 30 days.”

‍ ‍

False.

‍ ‍

The 30-day requirement commonly discussed under the Permit Streamlining Act relates to determining whether certain applications are complete, not necessarily approving the project.

‍ ‍

‍ ‍

“If the deadline passes, I automatically get my building permit.”

‍ ‍

False.

‍ ‍

Different laws have different consequences when deadlines are missed.

‍ ‍

‍ ‍

“Permit streamlining eliminates CEQA.”

‍ ‍

False.

‍ ‍

CEQA and permit processing are separate issues, although other California laws may provide CEQA exemptions or streamlining for qualifying projects.

‍ ‍

‍ ‍

“These laws only help large developers.”

‍ ‍

False.

‍ ‍

Many of California’s processing protections affect smaller housing developments as well.

‍ ‍

Understanding the applicable process can benefit homeowners, builders, and developers of many different project sizes.

‍ ‍

‍ ‍

Why This Matters

‍ ‍

California has increasingly recognized something developers have known for years:

‍ ‍

Uncertainty can kill a project just as easily as a denial.

‍ ‍

A developer can budget for a known requirement.

‍ ‍

It’s much harder to budget for an approval process with no predictable endpoint.

‍ ‍

California’s permit streamlining laws are designed to create greater certainty by establishing:

‍ ‍

·       Completeness deadlines.

‍ ‍

·       Decision deadlines.

‍ ‍

·       Limits on hearings.

‍ ‍

·       Objective review standards.

‍ ‍

·       Ministerial approval pathways.

‍ ‍

·       Greater accountability for local agencies.

‍ ‍

And according to HCD, the average time from development application to entitlement fell from approximately 160 days to 68 days between 2019 and 2024, a 57 percent reduction that the department attributes in part to streamlining reforms.

‍ ‍

‍ ‍

The Bottom Line

‍ ‍

Permit streamlining doesn’t eliminate the permitting process.

‍ ‍

It puts boundaries around it.

‍ ‍

For homeowners, that means greater transparency.

‍ ‍

For builders, it means more predictable scheduling.

‍ ‍

For developers and investors, it means better information about one of the most important variables in any project:

‍ ‍

Time.

‍ ‍

And in real estate development, time isn’t just an inconvenience.

‍ ‍

Time is money.

‍ ‍

‍ ‍

Looking Ahead

‍ ‍

In our next article, we’ll examine Lot Splits and Urban Housing and look more closely at how California has expanded opportunities to divide qualifying residential properties and create additional housing.

‍ ‍

If you’re dealing with a stalled application or evaluating the entitlement timeline for a development project, Buchanan Land Use Consulting can help identify the applicable permitting requirements, coordinate agency review, and keep the project moving forward.

‍ ‍

‍ ‍